Procedure
Clearance testing takes place while the area is still sealed off. If the result is too high, the area is cleaned again and measured again without fibres escaping into the surroundings.
- 1Final cleaning of the area by the remediation contractor
- 2Visual inspection: no visible residues or dust may remain
- 3Air sampling while settled dust is stirred up
- 4Analysis of the samples in the laboratory
- 5Release and removal of the enclosure, or further cleaning and a new measurement
Sampling
A pump draws a defined volume of air through a filter that collects the fibres. Flow rate, duration and number of samples depend on the measurement method and the size of the area.
So that the measurement reflects later use of the rooms, settled dust is stirred up during sampling, for example with fans.
Whether negative pressure stays on during the measurement depends on the national rules.
Analysis
The filters are analysed in the laboratory, by electron microscopy or phase contrast microscopy, depending on the method the national rules prescribe. Only electron microscopy can tell asbestos fibres apart from other fibres.
The result is given as a fibre concentration, in fibres per cubic metre (F/m³) or per litre (F/L). 1 F/L equals 1,000 F/m³.
Visual inspection and measurement are often carried out by a party independent of the remediation contractor. Who may do this is set by the national rules.